Need the work and and graph please !

Mathematics
1 answer:
Valentin [98]3 years ago
5 0
C is the correct graph because u can't get a cubed root of a negative number
if u chose 8 to bring x the cubed root is 2 and 2 - 3 = -1...graph matches
You might be interested in
a first number is 6 more than a second number. the first number multiplied by 2 is 8 more than the second number. what are the t
Andreas93 [3]

Answer:

-2 (negative 2)

Step-by-step explanation:

8÷2 =4

4-6 = -2

hope this helps

4 0
3 years ago
A poster is shown below: A rectangle is shown. The length of the rectangle is labeled 10 feet. The width of the rectangle is lab
Bumek [7]
6ft by 15 ft should be the correct answer
8 0
4 years ago
Read 2 more answers
Problem 11-93 Waltner Corporation s management... Waltner Corporation's management reports that its average delivery cycle time
Marat540 [252]

Complete question is;

Waltner Corporation's management reports that its average delivery cycle time is 25 days, its average throughput time is 7.7 days, its manufacturing cycle efficiency (MCE) is 0.43, its average move time is 0.3 day, and its average queue time is 3.00 days. Required: a. What is the wait time?

b. What is the process time?

c. What is the inspection time?

Answer:

A) Wait time = 17.3 days

B) Process time = 3.311 days

C) Inspection time = 0.789 days

Step-by-step explanation:

A) we are given;

Delivery cycle time = 25 days

throughput time = 7.7 days

The formula for wait time is calculated from;

Delivery time = wait time + throughput time

So, wait time = Delivery time - throughput time

Wait time = 25 - 7.7 = 17.3 days

B) The process time is calculated from;

MCE = Process time/throughput time

So, process time = MCE x throughput time

We are given MCE = 0.43,thus, and we already know throughput time. Thus;

Process time = 0.43 x 7.7 = 3.311 days

C) The inspection time is gotten from;

throughput time = Process time + Inspection time + Move time + Queue time

Making inspection time the subject;

inspection time = throughput time - Process time - Move time - Queue time

Move time = 0.3 days

Queue time = 3 days.

Thus;

inspection time = 7.7 - 3.311 - 0.3 - 3.3 = 0.789 days

3 0
4 years ago
Can someone help me with #4 please URGENT‼️
lesya [120]
Describe um it’s a line and has a F
4 0
3 years ago
What is 22 lb day in oz h?
yarga [219]
One pound is 16 oz. just multiply 22 by 16 and boom, there's your answer
3 0
3 years ago
Other questions:
  • Please help if you know the answer
    9·2 answers
  • Can someone please help me find the geometric sequence of
    13·1 answer
  • jeremy drew a polygon with four right angles and four sides with the same length.what kind of polygon did jeremy draw?
    8·1 answer
  • Please help! Question above (+10 points)
    12·1 answer
  • Plz help me plz if u get it correct i will mark brainlist if i can
    11·2 answers
  • Solve sin θ +1 = cos2 θ on the interval 0 less than or equal to θ less than 2pi
    10·1 answer
  • I’ll give you BRAINLEST PLEASE HELP
    10·1 answer
  • 2x+5=11 two step equations<br>​
    11·1 answer
  • What is 3x + 9?<br> (Ignore this part, says the question needs to be more than 20 characters)
    13·2 answers
  • Someone help me with this show work
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!