Answer:
B) Project B has below-average risk and an IRR = 8.5 percent.
Explanation:
Since the evaluation is based on IRR, use IRR rule that says you accept a project if its IRR > Cost of capital(WACC in this case)
Project A's IRR of 9% is < 10% WACC for average risk projects hence reject it.
Project B's IRR of 8.5% is > 8% WACC for below- average risk projects hence accept it.
Project C's IRR of 11% is < 12% WACC for above- average risk projects hence reject it.
Answer:
Scatter Diagram.
Explanation:
Scatter Diagrams are convenient mathematical tools to study the correlation between two random variables. As the name suggests, they are a form of a sheet of paper upon which the data points corresponding to the variables of interest, are scattered.
Answer:
The correct answer is Intranet.
Explanation:
An Intranet is a digital platform whose objective is to assist workers in generating value for the company, making available assets such as content, files, business processes and tools; facilitating collaboration and communication between people and teams.