Allushta [10]
4 years ago
3

You are using earned value analysis to track your project's progress. In your project, earned value is higher than planned value

and actual value. That means the project is _____ schedule and _____ budget.
Business
1 answer:
baherus [9]4 years ago
3 0

Answer: ahead of; under.

Explanation:

The Planned Value is the amount of money that is being allocated to complete a project. The Earned Value is the amount of work that the project has been able to achieve in reference to the original amount that was actually planned for the project.

Since we are told that the earned value is higher than planned value, it means that the project has been able to achieve a value that is more than the actual value planned for that period, therefore, the project is ahead of schedule.

Also, when the earned value is higher than actual value, it means that the project has been able to spend a lower amount for a certain amount of work than the amount that was budgeted for similar work, therefore we say it is under budget.

You might be interested in
The more companies an insurance company insures, the more likely they can predict the percentage of losses over a
Mumz [18]

Answer: C. Law of Large Numbers

Explanation:

The law of large numbers, posits that as the sample size grows, the mean of the samples will be closer to the average that's meant for the entire population.

According to the law of large numbers, when an experiment is repeated so many times, and then the results are averaged, the value that one gets will be close to the expected value.

In insurance, the more companies that are insured by the insurance company, the more likely they will b able to predict the percentage of losses over a given period of time.

5 0
3 years ago
statement? People can become part of a _______. When a person becomes part of an electrical______, that person can be shocked.
azamat
<span>An individual can become a part of a current. When that person becomes a part of that electrical current than that person will have electricity running through them which can result in the individual being shocked. It is unwise and very deadly unless the current is very minute.</span>
4 0
3 years ago
Read 2 more answers
Skidmore Music Company had the following transactions in March:
SVEN [57.7K]

Answer:

Please sew below

Explanation:

Skidmore Music Company.

1. Cash basis income statement

Sales

$13,800

Less: cost of goods sold

$1,700

Gross income

$12,100

Wages expense

$720

Operating income

$11,380

2. Accrual basis income statement

Sales.

$16,700

Less: cost of goods sold

$4,900

Gross income

$11,800

Wages expense

($720)

Utility expense

($280)

Operating income

$10,800

8 0
3 years ago
Fletcher Company collected the following data regarding production of one of its products. Compute the total direct materials co
pickupchik [31]

Answer:

Option (B) $3,570 unfavorable

Explanation:

Data provided in the question:

Direct materials standard (6 lbs. @ $2/lb.) =  $ 12 per finished unit

Actual direct materials used = 243,000 lbs.

Actual finished units produced = 40,000 units

Actual cost of direct materials used = $483,570

Now,

Total direct materials variance

= Budgeted cost of direct material - Actual cost of direct materials used

= ( 40,000 × $12 ) - $483,570

= $480,000- $483,570

= - $3,570

The negative value depicts Unfavorable

Hence,

Option (B) $3,570 unfavorable

5 0
3 years ago
Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to
SashulF [63]

Answer:

c) 5 days, 7 workers

Explanation:

The longest task is Task-1 which takes 5 days.

All the tasks are parallel. So, the length of the project should be 5 days. The resources employed are just the total of all the tasks i.e. 2+2+1+1+1 = 7.

5 days, 7 workers

7 0
4 years ago
Other questions:
  • PLEASE ANSWER WITH 100% THE CORRECT ANSWER ASAP IF YOU DON'T KNOW THE ANSWER THEN DON'T ANSWER
    10·2 answers
  • The law of increasing opportunity costs:_______a. refutes the principle of comparative advantage. b. applies to land-intensive c
    14·1 answer
  • Creating an endowment Personal Finance Problem On completion of her introductory finance​ course, Marla Lee was so pleased with
    12·1 answer
  • The particular market segment your company is trying to sell your products or services to is your _________.
    14·1 answer
  • Backstreets Co. recently acquired all of Jungleland Inc.’s net assets in a business acquisition. The cash purchase price was $6.
    7·1 answer
  • Steve was wrongfully terminated by Sam, his former boss at Big Flop, Inc., falsely stating that Steve embezzled money. When Stev
    10·1 answer
  • Compute net income for 2019 by comparing total equity amounts for these two years and using the following information: During 20
    8·1 answer
  • 4. You may think of your college or university as an organization that offers a line of different educational products. Assume t
    14·1 answer
  • Which type of loan requires that you pay the interest accumulated during college?
    7·1 answer
  • Click this link to learn about a career as a Multimedia Artist. What are some common tasks? Check all that apply.
    15·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!