Beep bop I’m a beginner and need this
Hshaks jdlsmavsusksns those were so that you would reach the answer minimum of 20 characters
Answer:
The final balance is $571.61.
The total compound interest is $121.61.
Step-by-step explanation:
hope this helps!
Answer:
(c) $3,93 more
(b) Mr. Sánchez's class earned more money.
(a) ![\displaystyle [42, 37] → [j, p]](https://tex.z-dn.net/?f=%5Cdisplaystyle%20%5B42%2C%2037%5D%20%E2%86%92%20%5Bj%2C%20p%5D)
Step-by-step explanation:
{79 = p + j
{118,17 = 1,65p + 1,36j
−25⁄34[118,17 = 1,65p + 1,36j]
{79 = p + j
{−86 121⁄136 = −1 29⁄136p - j >> New Equation
__________________________

[Plug this back into both equations above to get the j-value of 42]; 
The next step is to plug the solution into the BOTTOM EQUATION to calculate the total money earned for each class:
<u>Sánchez's class</u>
![\displaystyle 61,05 = [37][1,65]](https://tex.z-dn.net/?f=%5Cdisplaystyle%2061%2C05%20%3D%20%5B37%5D%5B1%2C65%5D)
Altogether, <em>thirty-seven</em> fruit pies cost $61,05.
<u>Kelly's</u><u> </u><u>class</u>
![\displaystyle 57,12 = [42][1,36]](https://tex.z-dn.net/?f=%5Cdisplaystyle%2057%2C12%20%3D%20%5B42%5D%5B1%2C36%5D)
Altogether, <em>forty-two</em> bottles of fruit juice cost $57,12.
* Based on the calculation, it is perfectly clear that Mr. Sánchez's class earned more money by $3,93:

I am delighted to assist you anytime my friend!
In 6 weeks.
For this problem, you need to determine
the least common multiple of the numbers given which is 2, 3, and 6. You
can calculate the LCM of multiple numbers by pairs.
The LCM of 2 and 3 is 6 because 6 is the smallest possible number that can be evenly divided by both 2 and 3.
Now you need the LCM of 6 and 6. Which is also 6, because 6 is the smallest number that can be evenly divided by 6.
So the LCM of 2, 3, and 6 is 6. So in 6 weeks, Clea will once again
have a music less, attend dance class, and have a dental appointment,
all during the same week.
Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days