Option D
He is probably using Indirect questions information seeking tactics
<u>Explanation:</u>
Indirect questions are a more formal process to demand erudition or perform requests. We regularly practice them when requesting something of immigrants or people we do not know well, including coworkers. Hinting is an indirect tactic.
It often transpires with questions about job execution. They are face-saving tactics. Indirect questions are a way of being respectful. We also practice them when requesting support from friends or when we desire to evade sounding demanding. But, some indirect questions do not exist wh-question words.
Answer:
$334,101.43
Explanation:
The computation of the value of this company is shown below:
Value of unlevered firm= [$63,300 × (1 - 23%)] ÷ 14.7%
= $331,571.43
And,
Value of this company = 331,571.43 + 23% of $11,000
= $331,571.43 + $2,530
= $334,101.43
As we know that value of the company is the mix o f levered firm and the unlevered firm according to that we done the calculations
Answer:
Expected Loss will be $3
Explanation:
Expected Loss can be calculated by multiplying the probabilities to Net expected outcome.
Probabilities
Prize ( $460) = 1 / 100
Prize ( $80 ) = 2 / 100
Prize ( $20 ) = 4 / 100
No prize = 100/100 - (1+2+4)/100 = 93/100
Expected value = [( 460 - 10 ) x 1/100 ] + [( 80 - 10 ) x 2/100 ] + [( 20 - 10 ) x 4/100 ] + [( 0 - 10 ) x 93/100] = 4.5 + 1.4 + 0.4 - 9.3 = -$3
Answer:
The answer is "205,241"
Explanation:
Its relative value operation:
Smooth skin Seedling Skin Total
A Unit sold 
selling price per unit
Sales value 
Join its cost allocate

Smooth Skin is assigned the combined costs within each development process by way of the relative cost process 205,241
Answer: Resource levelling
Explanation:
Resource levelling is a term used in project management defined and is defined as a technique used where there is adjustment in the start and finish dates based on limitation in resources with the aim of balancing the demand for resources using the available supply.
While performing activities in project planning, the manager will try to schedule some tasks simultaneously. Resource leveling can be used to balance the workload of the main resources during the duration of of the project usually at the expense of either the time, cost or scope.