Answer:
Option (a) is correct.
Explanation:
Contribution margin per marketing plan = Sales - Variable cost
= $3,000 - $2,000
= $1,000
A.
(1) 

Break even in marketing plan = 400
(2) Break-even in dollars:
= Break-even in marketing plan × Average rate per plan
= 400 × 3,000
= 1,200,000
(3) Margin of safety = Actual sales - Break-even sales in dollars
= 1,500,000 - 1,200,000
= 300,000


= 20%
B.
(1) Contribution margin per marketing plan = Sales - Variable cost
= $4,000 - $2,000
= $2,000


Break even in marketing plan = 200
(2) Break-even in dollars:
= Break-even in marketing plan × Average rate per plan
= 200 × 4,000
= 800,000
(3) Margin of safety = Actual sales - Break-even sales in dollars
= 1,500,000 - 800,000
= 700,000


= 47%
Therefore, option (a) would achieve the margin of safety ratio more than 45%.
Answer:
r= 3
Explanation:
Due that the level price does not changed, the first thing that you have to do to find the equilibrium is put the two equations with an equal
Money demand =Supply of money
2,200 – 200 r= 2,000
Now you have to find the value of r and you have to clear the formula and first you have to:
2,800- 2,200 = 200r
Now that you have the number together you have to apply the operation
600 = 200r
As the 200 is multiplying the r you have to pass the 200 to divided the 600
r= (600/200)
r= 3%
The interest rate is 3%
Answer: c) $7,535
Explanation:
The Collection Float refers to the time that it takes for a deposited check to become available to the account owner after the check has been deposited.
The Average amount is calculated thus;
= No. of payments * Clearing days * average value of payment
= 138 * 1.3 * 42
= $7,535
Answer:
The correct answer is letter "B": seeks to ensure the future performance of the project work is aligned with the project management plan.
Explanation:
Preventive actions are defined as those that aim to mitigate risks inherent in the operations of a business. Preventive actions lead to entities creating contingency plans that allow them to have certain strategies in front of unexpected situations that could harm the firm's operations.
<em>The project risk management plan is the reference that prevention actions take at the moment of recognizing the set of activities that should be followed to ensure the optimal future performance of a project.</em>