Answer:
13
Step-by-step explanation:
I'm not sure what the question is here. If an answer is communicative property, go with that. If it is asking for
, the answer is about 84.8230016469.
Answer:
19 hrs
Step-by-step explanation:
t varies inversely with number of people p
t = k/p
If it takes 7.125 hrs for 8 workers to do the job
K = tp
= 7. 125 x 8
= 57
How many hours will it take if there are 3 workers .
Recall t = k/p
t = 57/3
= 19 hrs
Therefore, It’ll take 19 hrs to Complete the job if there are only three workers.
Answer:
Step-by-step explanation: