Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.
Answer: 927
Step-by-step explanation:
Answer:
substitute 8 into x =(8-2)2
(6)2=12
Answer:
x=1056.25
Step-by-step explanation:
(2x)(2x)(55)=(65)(65)(55) Multiply
4x(55)=232375 Divide 55 from each side
4x=4225 Divide each side by 4
x=1056.25
You multiply 8.5 by 5.25 by 4 and get 178.5