Answer:
a. operands are evaluated left toright. 7
b. operands are evaluated right toleft. 12
Explanation:
a. operands are evaluated left toright. 7
b. operands are evaluated right toleft. 12
left to right
int fun (int *i) {
*i +=5; we add 5to x making x 8
return4; we return 4 tomain
}
void main ( ) {
int x = 3;
x = x + fun(&x); x starts at 3 in fun it ischanged to 8 but the 3 is already being used the 4 fromfun is added (3+4) to it making it 7
}
right toleft x starts at 3 in fun x gets changed to 8 and fun is returned as 4so we have 4 + 8 = 12
Paraphrasing
left to right it's is 3 + 4 =7 original value of x is used
right to left it is 4 + 8 =12 x is used as it was changed by fun, since fun was alreadyexecuted
Answer:
Hi there! The answer is C:
Explanation:
The scope of the LOWER function is limited to the select clause it is being used in. Outside of the select statement, the column will be returned as it is currently present in the database. Using the LOWER function will not automatically store data in lower case letters in the database tables. As an exercise, try creating a simple database table called "Employees" with columns "id" and "name". Then input a row using an insert statement with id as 1 and name as "BLAH". Try using the select statement with LOWER function and then without the LOWER statement.
Answer:
The maximum value that are represented as unsigned n -bit binary integer is
. The unsigned binary integer refers to the fixed point of the system that does not contain any fractional digits.
The unsigned binary integer contain module system with the power 2. The number of student table in the class is the best example of the unsigned integer. The numbers can be represented by using the binary notation and bits in the computer system.
Mike needs to write the primary objectives of a project in a project plan. He should write this under the SCOPE section of the project plan.
Explanation:
- Project scope is the part of project planning that involves determining and documenting a list of specific project goals, deliverables, features, functions, tasks, deadlines, and ultimately costs.
- It is what needs to be achieved and the work that must be done to deliver a project.
- The Scope of Work (SOW) is the area in an agreement where the work to be performed is described.
- The SOW should contain any milestones, reports, deliverables, and end products that are expected to be provided by the performing party. The SOW should also contain a time line for all deliverables.
- The scope is simply all the work that needs to be done in order to achieve a projects objectives.
- A project scope, or project scope statement, is a tool used to describe the major deliverables of a project including the key milestones, high level requirements, assumptions, and constraints.