An economy is operating at full employment, and then workers in the bread industry are laid off. this change is portrayed in the movement from C to F.
The economy in points A, B, C, and D is at full employment. Some employees make bread, while others make wine. Points F and G depict scenarios where the unemployment rate varies depending on the state of the economy. Point E illustrates a growing economy that is performing above its maximum level of employment. When the unemployment rate is between 4% and 5%, an economy is considered to be in full employment; nonetheless, frictional unemployment is always present.
Given that the economy was at full employment when the question was asked, but that unemployment then rose, the starting point must be A, B, C, or D, and the final position must be F or G. Only option D, from points C through F, makes sense.
An economy is operating at full employment, and then workers in the bread industry are laid off. this change is portrayed in the movement from C to F.
To learn more about the above question, visit the following link:
brainly.com/question/14549969
#SPJ4
Answer:
C. business reply
Explanation:
In the case when we have to increase the no of orders that could be received via direct mail adverstising and the customer could use the special kind of envelope for mailling the orders so this should be an example of business reply mail as it is concerned with the business and here the orders are to be an important factor that becomes very important for the company.
Therefore the option c is correct
customer complaints and suggestions
Answer:
The correct answer is B
Explanation:
The journal entry which is to be recorded for the service revenue at the end of May is as follows:
Unearned Revenue A/c..............Dr $5,333
Service RevenueA/c...........Cr $5,333.
Working Note:
Revenue = Total amount × Number of months / Total months
where
Amount is $8,000
Number of months means at the end of May which is a 2nd month
Total months is 3 months (April, May and June)
= $8,000 × 2 / 3
= $5,333
Under project planning activities, defining what leads to successful completion is a part of <u>DURATION.</u>
Duration is the sum of the workdays, hours, or weeks necessary to finish a job. The length is determined by the resources' capability and availability. The amount of effort required to finish a task, or the actual time spent working on the project, is measured in person hours.
<h3><u>How is project duration calculated?</u></h3>
- We must know how to estimate duration while creating a timetable. We might simply compute our projected project length by taking the number of effort hours, divided by the number of resources, assuming everyone worked eight hours each day and was completely productive throughout all eight hours.
To know more about duration in a project, check the given links.
brainly.com/question/11375376
#SPJ4