Answer:
Step-by-step explanation:
Required man days to complete the job = 8 * 6
= 48 Man Days
Required labors to complete the job by 15 days = 48/15
= 3.2
It means, it is required 4 labors can complete the certain work by 15 days
Answer:
888.89 km
Step-by-step explanation:
Write the given question as an equation and solve.
80 km = 0.09 × (what distance)
(80 km)/0.09 = what distance . . . . . divide by the coefficient of the variable
888.89 km ≈ what distance
80 km is 9% of 888.89 km
Answer:
option (D) 16.5
Step-by-step explanation:
Data provided:
Sleep time of , X = 15.9 is at the 10th percentile
Standard deviation, σ = 0.5 hour
also,
10th percentile of normal distribution is
Z = F⁻¹(0.10)
or
Z = - 1.28 (Using Standard Normal distribution)
Now,

or
X = μ + ( σ × Z )
or
μ = X - ( σ × Z )
on substituting the respective values, we get
μ = 15.9 - 0.5 × (-1.28)
or
μ = 16.5
Hence, the correct answer is option (D) 16.5
Answer:
D
Step-by-step explanation:
1. calculate the expression
2.multiple reorder
3.remove parenthesis
Answer:
the X represents the width, since to get the area, you have to multiply length times width
Hope that helps!