Answer:
Jim's path is the critical path on this activity graph.
Step-by-step explanation:
Critical Path:
Critical path is the the longest path in the project task paths. It shows the least amount of time in which project can be completed. It can be find by looking at the longest path in the network diagram of the project; not in term of nodes or activities instead in term of days.
In given case:
Path 1 Bill task's total duration= 6 days
Path 2 Jim's task's total duration= 17 days
Path 3 Betty task's total duration= 7 days
Path 4 Cynthia task's total duration= 14 days
Hence the longest path i.e. critical path is of Jim's activity path !
Answer:
distance rate time
trip to park 24 14 25
return 30 27 25
the jogger's speed is 24
Step-by-step explanation:
Answer:
o,-3 and 1.5,0
Step-by-step explanation:
You can find a calculator on a website called Desmos that might help answer related questions.
Answer:
56.1 cm²
Step-by-step explanation:
In any circle the area (A) of a sector is
A = area of circle × fraction of circle
= πr² × 
= π × 8.91² × 
=
≈ 56.1 cm²
Answer:
46
Step-by-step explanation:
64 spaces. 18 empty
64 - 18 = 46