Answer:
A Swedish court said Friday that rapper ASAP Rocky will be detained for another week as prosecutors decide whether to formally charge him following a fight last month in downtown Stockholm.
The rapper, born Rakim Mayers, has been in Swedish custody, along with two of his associates, since early July after a June 30 altercation that Rocky’s supporters say he tried to avoid. Under the court’s decision Friday, the men could be detained until at least July 25.
Concerns have mounted for the men amid reports that they are being held in “inhumane conditions,” including long daily periods of solitary confinement. A growing number of lawmakers and celebrities, including Kim Kardashian and Kanye West, has called for their release.
Answer:
y=3
Step-by-step explanation:
Multiply 9 from both sides to cancel it out.
-27=-y/9
/9 /9
-3=-y
We can't have a negative variable, so we divide -1 from both sides.
-3=-y
/-1 /-1\
3=y
-hope it helps
Answer:
y=42
Step-by-step explanation:
y+48+90=180
y=180-138
y=42
I believe you meant "why is the number of shifts multiplied by approximately 4.5 to obtain the total number of operators required to run the plant"
Answer and Explanation:
There are 3 shifts per day, 49 weeks per year and 5 shifts per operator per week
To get total number of operators required to run the plant, we multiply number of shifts in a year by number if operators per shift.
49 weeks×5 shifts= 245 shifts per operator per year
365×3 shifts= 1095 shifts per year
1095/245=4.5 operators per shift
total number of operators required to run the plant(per day) = 4.5×3= 13.5 approximately 14
total number of operators required to run the plant(per year) =4.5×1095=4927.5 approximately 4928