Answer:
The correct answer is c) secondary
Explanation:
The term Secondary data refers to the information that has been collected by someone different than the user. For example, the information collected by government departments sometimes appears on the internet, if any user takes this information from the internet and uses it on any homework, project, business, etc... It is considered such as secondary data.
Answer:
D. possibly increase, possibly decrease, or possibly remain constant
Explanation:
If a firm's expected growth rate increased then its required rate of return would possibly increase, possibly decrease, or possibly remain constant
Answer:
The correct answer is programmed.
Explanation:
Also called unstructured, they are decisions that are taken in the face of problems or situations that occur infrequently, or those that need a specific model or process of solution, for example: “Launching a new product to the market”, in this type It is necessary to follow a decision-making model to generate a specific solution for this particular problem.
Programmed decisions address rare or exceptional problems. If a problem has not been presented frequently enough to be covered by a policy or if it is so important that it deserves special treatment, it should be handled as an programmed decision. Problems such as allocating the resources of an organization, what to do with a production line that failed, how to improve relations with the community - in fact, the most important problems that the manager will face - will usually require programmed decisions.
Question: The question is incomplete. See the full question below and the answer.
You are an up-and-coming developer in downtown Seattle and are interested in constructing a building on a site you own. You have collected four bids from prospective contractors. The bids include both a cost ($millions) and time to completion (months):
Contractor Cost Time
A 100 20
B 80 25
C 79 28
D 82 26
The problem now is to decide which contractor to choose. B has indicated that for another $20 million, he could do the job in 18 months, and you have said that you would be indifferent between that bid and the original proposal. In talking with C, you have indicated that you would just as soon pay her an extra $million if she could get the job done in 26 months. Who gets the job? Explain your reasoning. (It may be convenient to plot the four alternatives on a graph.)
Answer:
See the explanation for the answer and find attached of the graph.
Explanation:
So we draw a regression line of Time vs Cost and best fit a curve based on the data given, given in the above figure. The four alternatives are marked in the figure as well. Our main objective is to reduce both time and cost, but that might not be possible So the best thing would be to look for alternatives which lie below the line. If C gets an extra million, then that point would come below the regression line, and it would be a better alternative than D, because for the same time we are getting the job done at a cheaper cost.
Also if B is paid extra 20 million, that point also comes below the regression line, and hence will be a better alternative than A because for the same cost again we are getting the job done earlier. We need to choose between B and C. Now in order to optimise both cost and time, we need to choose a point close to the middle point of the regression line segment in 1st quadrant. We see that C is much more closer to the middle point and hence seems like a better option.
So we choose C as our contractor if we consider B's alternative bid, but if we do not consider B's alternative bid and stick to the original one, we choose B as our contractor.
Answer:D
Explanation:The answer is D because the value of a common stock depends on the amount the stock was purchased for and the amount it was sold for.