Answer:
Setup time = 2.5 min. per order
Process capacity = 1.09 units/minute
Utilization = 7.5 minutes
Explanation:
The time to cook just one order = 3 minutes
Cooking two orders in a batch = 3.5 minutes
cooking three orders = 4 minutes
bagging and accepting payments = 0.80 minutes
a) Setup time:
Setup time = 3 - 0.5
= 2.5 min. per order
b) Process capacity:
Production = Setup time + ( Processing time * Batch size )
= 2.5 + (0.5 * 6)
= 5.5 minutes
Process capacity = Batch size / Production
= 6 / 5.5
= 1.09 units/minute
c) Utilization:
Batch size = 10
Production = Setup time + (Processing time * Batch size)
= 2.5 + (0.5 * 10)
= 7.5 minutes
AP courses are part of the College Board organization that requires students to take a rigorous test at the end of the course to potentially earn college credit. A dual credit course on the other hand is an official course at Loyola University Chicago.
Answer:
Customer satisfaction is a term frequently used in marketing. It is a measure of how products and services supplied by a company meet or surpass customer expectation.
Explanation:
~hope this helps