Answer:
The risk consequence of both activities is 1.6 months.
Step-by-step explanation:
We can define a randome variable D: total delay time for the project, and calculate its expected value.
This would be the risk consequence of both activities.
The expected delay time for the project is the sum of the expected delay for task A plus the expected delay for task B. It is assumed the likelihood of a problem in any task is independent of the other.
Then, each expected delay for a task is equal to the probability of a problem multiplied by the consequence (delay time).

The risk consequence of both activities is 1.6 months.
10(the number of tests) divided by 5(the amount of weeks)=2. That is 2 tests every week. 2x7 weeks is 14 tests.
Or this could be a trick question and he could have only had tests for 5 weeks.
This is the concept of algebra, to solve the question we proceed as follows;
the current number of women is:
1/4*20=5 women
the percentage of women is:
1/4*100=25%
therefore for the team to have 40% women, the number of women should be:
40/25*5
=8 women
The answer is 8 women