Is this a multiple choice
Answer:
R = 2414 units
0.794
Step-by-step explanation:
Given:
Weekly demand, D = 331 units
Lead time (L)= 6 weeks
Standard Deviation (SD) = 85 units
The reorder point is calculated using the relation :
R = D*L + z*(SDw)
SDw = the standard deviation with lead time of 6 weeks ; √6 * 85 = 208.21
z = NORMSINV(0.98) = 2.05
R = (331 * 6) + (2.05 * 208.21)
R = 1986 + 428.122
R = 2414.122
R = 2414 units
The Safety stock, SS
SS = z * SDw
SS = 2.05 * 208.21
SS = 426.8305 units
60% reduction :
426.8305 * (1 - 60%)
= 170.7322
= 171 units
The new service probability ;
SS = z * SDw
171 = z * 208.21
z = 171 / 208.21
z = 0.82
P(Z < 1.02) = 0.7938 = 0.794 = 79.4%
Answer: 4 1/5
Step-by-step explanation:
Rewriting our equation with parts separated
=2 + 3/5 + 1 + 3/5
Solving the whole number parts
2 + 1= 3
Solving the fraction parts
3/5 + 3/5 = 6/5
Simplifying the fraction part, 6/5,
6/5 = 1 1/5
Combining the whole and fraction parts
3 + 1+ 1/5 = 4 1/5
Solution by Formulas
converting mixed numbers to fractions, our initial equation becomes,
13/5 + 8/5
Applying the fractions formula for addition,
=(13 × 5) + (8 × 5)/5 × 5
=65+40 / 25
=105/25
Simplifying 105/25, the answer is
=4 1/5
Answer:
b=−12
Step-by-step explanation: