Answer:
the minimum price it should charge is $40 per unit.
Explanation:
Minimum Transfer Price = Variable Costs - Internal Savings + Opportunity Cost
<em>Note : Division A has capacity available to meet B's requirements therefore there is no opportunity cost</em>.
There are Internal savings of $5 as A's variable costs will be $5 less per unit.
Minimum Transfer Price = $45 - $5
= $40
The calculated profit per unit for base-case, worst-case is, and best-case for the management of Brinkley corporation is:
<h3>The Profit per unit for base-case:</h3>
45 - 1 1- 24 - 3 = $7
<h3>Profit per unit for worst case:</h3>
45 - 12 - 25 - 3 = $3 per unit
<h3>Profit per unit for best case:</h3>
45 - 10 - 20 - 3 = 12$ per unit
b. The mean profit per unit is given as $7.05
c. The reason the simulation approach is preferable is due to the fact that it can help to determine the probability of profit as a particular amount, unlike the what-if scenario analysis.
It can also create different scenarios for possible resources.
d. The probability of the fact that the profit per unit woul be less than 5 is 9%
Read more on risk analysis here: brainly.com/question/6955504
The correct answer is exchange or trade
Answer:
C. sequencing and allotting time to all project activities
Explanation:
This will be part of the Project schedulling phase on which the uhman and materials resources are allocate to complete the activities within the timeframe of the project.
Asinging time to the project activities is part of the project schedulling phase.
While within Project controlling are the activities that check how the project is going. It looks for deviation on the expected outcome and notifies to managment. It must ensure the quality, quantity and cost of the goals