Answer:
manufacturing activities
Explanation:
Manufacturing activities refers to the manufacturing, testing, processing, and other kind of activities
Here the required things to be undertaken by its supplier so that it can manufactured and supply to the client
SO as per the given situation, the early outsourcing efforts should be confined to the manufacturing activities
Answer:
The correct answer is: decrease.
Explanation:
If Aggregate Supply (<em>AS</em>) is higher than Aggregate Demand (<em>AD</em>), it implies somehow consumers are keeping their income with them. Economic activity will <em>contract </em>as a result but to promote consumption, for instance, banks lower their interest rates on loans with the confidence that consumers will have enough money to cover their debts.
Answer:
A perfectly competitive firm will minimize its losses by shutting down when: P < TFC at the profit-maximizing level of output. P < MC at the profit-maximizing level of output.
Explanation:
A firm will choose to implement a production shutdown when the revenue received from the sale of the goods or services produced cannot cover the variable costs of production. In this situation, a firm will lose more money when it produces goods than if it does not produce goods at all. Producing a lower output would only add to the financial losses, so a complete shutdown is required. If a firm decreased production it would still acquire variable costs not covered by revenue as well as fixed costs (costs inevitably incurred). By stopping production the firm only loses the fixed costs.
The expected completion time of a project is 40 weeks and the variance of its critical path activities is 9.Project completion time is 42.0325 weeks.
Variance of its critical path activity 9 weeks.
Therefore, Standard deviation of its critical path activity = Square root ( variance) = Square root (9) = 3
Project completion time with 5% certainty means probability of project completion - 0./5 Corresponding z value for probability of 0.75 = NORMSINV ( 0.75) = 0.6745
Therefore, project completion time with 75% certainty = Expected completion time of the project .
Value x Standard deviation of critical path activity = 40 weeks * 0.6745 x 3 weeks = 40-2.0235 = 42.0325 weeks
Learn more about Variance here
brainly.com/question/15858152
#SPJ4
Answer:
$72,000
Explanation:
Given that,
Partnership earned revenue = $900,000
Operating expenses = $660,000
Withdrawal by Wayne = $90,000
Additional investment by Wayne = $30,000
Wayne's gross income from the partnership is:
= Tax rate × (Earned revenue - Operating expenses)
= 30% × ( $900,000 - $660,000)
= 0.3 × $240,000
= $72,000