Evaluate ab + c for a = 2, b = 3, and c = 4. 9 10 27

Mathematics
1 answer:
Lilit [14]3 years ago
6 0

Given that a = 2, b = 3, and c = 4.

To evaluate ab+c, we will plug given values as shown below

ab+c

=2*3+4

=6+4

=10

Hence final answer is 10.

You might be interested in
15 Points!
AveGali [126]
=  (-19)* pi / 6  * 180 / pi   = -570 degrees
6 0
4 years ago
Read 2 more answers
Melody lives 30 miles due south of her cousin's house and 40 miles due west of her grandparents' house. One
patriot [66]

Answer:

my bad g I don't know thus I just need some points

4 0
2 years ago
Problem 11-93 Waltner Corporation s management... Waltner Corporation's management reports that its average delivery cycle time
Marat540 [252]

Complete question is;

Waltner Corporation's management reports that its average delivery cycle time is 25 days, its average throughput time is 7.7 days, its manufacturing cycle efficiency (MCE) is 0.43, its average move time is 0.3 day, and its average queue time is 3.00 days. Required: a. What is the wait time?

b. What is the process time?

c. What is the inspection time?

Answer:

A) Wait time = 17.3 days

B) Process time = 3.311 days

C) Inspection time = 0.789 days

Step-by-step explanation:

A) we are given;

Delivery cycle time = 25 days

throughput time = 7.7 days

The formula for wait time is calculated from;

Delivery time = wait time + throughput time

So, wait time = Delivery time - throughput time

Wait time = 25 - 7.7 = 17.3 days

B) The process time is calculated from;

MCE = Process time/throughput time

So, process time = MCE x throughput time

We are given MCE = 0.43,thus, and we already know throughput time. Thus;

Process time = 0.43 x 7.7 = 3.311 days

C) The inspection time is gotten from;

throughput time = Process time + Inspection time + Move time + Queue time

Making inspection time the subject;

inspection time = throughput time - Process time - Move time - Queue time

Move time = 0.3 days

Queue time = 3 days.

Thus;

inspection time = 7.7 - 3.311 - 0.3 - 3.3 = 0.789 days

3 0
4 years ago
Write an equation in point-slope form of the line using points D(0,5),E(5,8)
zhenek [66]

Answer:

<em>8 - 5 = m(5 - 0)</em>

Hope that helps you! :)

8 0
3 years ago
The Statue of Liberty is 305.5 feet tall from the foundation of its pedestal to the top of its torch Isla is building a model of
Amiraneli [1.4K]
Idk if you can help me on my answer that would be helpful
6 0
4 years ago
Read 2 more answers
Other questions:
  • A family purchased tickets for a concert. They paid a total of $90 for 7 adult tickets and 12 child tickets. The price of a chil
    12·1 answer
  • #6) PLEASE HELP WITH QUESTION! MARKING BRAINLIEST.
    8·2 answers
  • A circle has it's center at (-4,5) and a radius of 7 units. What is the equation of the circle?
    15·1 answer
  • A set of stairs is being built as shown. The length of each stair is 11 inches. What is the rise, r, for each stair? Round to th
    5·2 answers
  • Does anyone know how to do these word problems?
    13·1 answer
  • Heladio has 52 marbles . divide them into two groups so that for every 6 marbles in the first group there are 7 marbles in the s
    15·1 answer
  • W is less than -3 and greater than or equal to -7
    7·1 answer
  • Divide. help due its 11:59 tonight
    5·1 answer
  • -3 to the 3rd power + 2
    14·2 answers
  • 60÷12 :)<br> Simple question!
    10·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!