Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.
Answer:
- Annie- 17 hours, Brian- 3 hours
Step-by-step explanation:
Let the number of hours Annie travelled be a, and same of Brian be b
<u>Then we have</u>
<u>Substituting a in the first equation</u>
- 5b + 2 + b = 20
- 6b = 20 - 2
- 6b = 18
- b = 3
<u>Then finding a</u>
<u>So the answer is:</u>
- Annie- 17 hours, Brian- 3 hours
Answer:
B. F:S = 17 to 19; S:F = 19 to 17
Step-by-step explanation:
Put the corresponding numbers in the corresponding parts of the ratio you want to write:
freshmen to sophomores (F:S)
17 to 19
___
sophomores to freshmen (S:F)
19 to 17
These pairs of numbers match choice B.