Answer:
D) infant mortality
Explanation:
Infant mortality rate (IMR) is a ratio that measures how many infants (children under one year of age) die for every 1,000 live births. The IMR serves as an indicator of how healthy a country's population is.
The countries with the highest IMR are Afghanistan, Somalia, Central African Republic. While the countries with the lowest IMR are Japan, Iceland and Singapore.
Answer:
Baker Industries
The Cost of goods sold for the period is:
= $330,000
Explanation:
a) Data and Calculations:
Cost of goods manufactured $ 320,000
Beginning finished goods inventory 45,000
Ending finished goods inventory 35,000
Cost of goods sold:
Beginning finished goods inventory $45,000
Cost of goods manufactured 320,000
Ending finished goods inventory (35,000)
Cost of goods sold = $330,000
Keeping the appropriate cash flow in the cash flow register, using a financial calculator, NPV should be calculated for taking the decision.
Answer: According to the NPV calculated, Chen should buy a new machine.
<u>Explanation:</u>
Cash outflow = $40000
Increase in annual after-tax cash flows : CF = $9000
Place the cash flow on a time line:
0 1 2 10
I 10 I I . . . I
-110000 19000 19000 19000
With a financial calculator, input the appropriate cash flow into the cash flow register, input I/YR = 10, and then solve for NPV. The answer for NPV is $6746.78.
Thus, Chen should buy a new machine.
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.