Answer:
Explanation:
Given weekly demand = 1200 units
Number of weeks per year = 45
Annual demand (D) = weekly demand × number of weeks per year = 1200 × 45 = 54,000 units
Ordering cost(C) = $55
Holding cost (H) = 25% of purchase price = 25% of $3.20 = 0.25*$3.20 = $0.8
EOQ = √(2DC/H) = √[(2 × 54,000 × 55) / 0.8] = √(5,940,000/0.8) = √7,425,000 = 2,725 units
Answer is D - 2,725 units
Answer: Liability of $300,000
Explanation:
In the question above, what we have is a deferred tax liability, which could be explained as the amount accrued in taxes at a present time but payable in the future. The tax rate will not be based in the present tax rate. Thus is why we will not be using the 30% tax tate of 2018 in calculating the tax amount.
Tax rate = 40%
Exceeded tax basis = $750,000
0.4 × 750,000 = $300,000
Therefore, Johns-Hopper should report the deferred tax effect of this difference in its December 31, 2018, balance sheet as Liability of $300,000
Answer:
The correct option is C states that creditors have a higher position in the priority of claims.
Explanation:
If I am hired as brand manager I would do the following:
Step 1: To conduct an analysis with Production team & Sales Team
This step serves as the base to understand the challenges, process and the victory achieved so far. The aim is to promote the product. So it is necessary to analyze the challenges from both production team and mainly with sales team. I would do an analysis and find possible ways to fix those.
Step 2: Conduct a training program associated with step 1
After analyzing the possible way, since I don't have a direct control over the team, I would conduct a training program and will list down ways to face the challenge and promote the product. It will be conducted as a "Knowledge-sharing session"
Step 3: Concentrate on advertisement too
The best way to reach the product is through advertising through the media. The best advertisement can attract people and bring business.
Step 4: Re-analysis: This is where an hand-holding process gets initiated and continue through out. Once again go back to step 1 and the process continues.
Answer:
The Answer is d. the tendency for project scope to keep getting bigger and bigger.
Explanation:
A scope refers to all the work involved in creating the products of the project and the processes used to create them.
A scope creep refers to changes, continuous or uncontrolled growth in a project's scope, at any point after the project begins. This can occur when the scope of a project is not properly defined, documented, or controlled.
Hence the answer is d. the tendency for project scope to keep getting bigger and bigger.