Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).
Step-by-step explanation:
y = -2x + 1. => Slope = -2
Then the perpendicular line will have a slope of -1/(-2) = 0.5.
We have y = 0.5x + c.
When x = 4, y = -3.
=> (-3) = 0.5(4) + c, c = -5.
Hence the answer is y = 0.5x - 5. (C)
People don't actually know this, but it isn't 4, it's 22. If Base+ball is Baseball, then 2+2 is 22
I hope this helps!
Answer:
Discount = $290.76 × 0.2 = $58.15
Cost After Discount = $290.76 - $58.15 = $232.61
Sales Tax = 0.0625 × $232.61 = $14.56
How Much You Pay = $232.61 + $14.56 = $247.17
Step-by-step explanation:
Discount:
290.76 × 0.2* = 58.152
Round that to 58.15
* Turn 20% into a decimal (0.2)
Cost after Discount:
290.76 - 58.15 = 232.61
Sales Tax:
First turn 6.25 % into a decimal. Which would be 0.0625.
0.0625 × 232.61* = 14.556875
Then we round to the nearest hundredth and you get 14.56.
* We us the amount after the discount instead of the original price.
How much you pay:
232.61 + 14.56 = 247.17