Answer:
X= -5/3 Y= 10/3
Let me know if you need the work to be shown
16% × 65 = 10.4
i am a mathematics teacher. if anything to ask please pm me
Answer: the percent value-added time for this ride is 16.67%
Step-by-step explanation:
Given that;
Waiting time for Vera = 35 minutes
Length of Vera's ride = 7 minutes
total processed time will; ( 35 + 7 ) = 42 minutes
the percent value-added time for this ride = ?
so
Percentage value-added time of Vera will be
= (length of the ride / total process time) × 100
we substitute
⇒ (7 / 42) × 100
⇒ 0.16666 × 100
⇒ 16.67%
Therefore the percent value-added time for this ride is 16.67%
You multiply 120 by 0.60 and you would get 72