let the customer drink it?
Answer:
b) internal rate of return will exceed its required rate of return.
Explanation:
The internal rate of return is the discount rate at which the NPV = 0. If the NPV is positive when calculated using the project's discount rate, then the IRR is going to be higher than the discount rate.
Option A is wrong because the profitability index (PI) of a project is calculated by dividing the present value of its cash flows by its cost. If the NPV is positive, it means that the present value of its cash flows will be greater than the costs, so the pI will be more than 1.
Option C is wrong because if the costs exceed the benefits, then the NPV will be negative.
Option D is wrong because that would mean that the NPV is negative.
Option E is something made up that doesn't make any sense.
Answer:
D. Sandals
Explanation:
Sandals aren't a preferred clothing item when going into a workplace, it's more informal than the other options provided.
Answer:
the total cost of ending work in process is $39,420
Explanation:
The computation of the total cost of ending work in process is shown below:
Equivalent cost per unit
Material = $301,600 ÷ 5,200 units = $58 per unit
Conversion = $405,500 ÷ 5,000 units = $81.10 per unit
Now ending work in process is
= 400 units × $58 + 200 units × $81.10
= $23,200 + $16,220
= $39,420
Hence, the total cost of ending work in process is $39,420