Answer:
The risk consequence of both activities is 1.6 months.
Step-by-step explanation:
We can define a randome variable D: total delay time for the project, and calculate its expected value.
This would be the risk consequence of both activities.
The expected delay time for the project is the sum of the expected delay for task A plus the expected delay for task B. It is assumed the likelihood of a problem in any task is independent of the other.
Then, each expected delay for a task is equal to the probability of a problem multiplied by the consequence (delay time).

The risk consequence of both activities is 1.6 months.
The equation is more than that numbor
Answer:
S={1, 1, 2, 2, 3, 4}
Probability of spinning a 1 = 1 in 3 or 33%
Step-by-step explanation:
The sample space is the set of all possible outcomes in an experiment. The outcomes here are the numbers in each section of the spinner: 1, 1, 2, 2, 3, 4. The sample space is:
S={1, 1, 2, 2, 3, 4}
Two out of six possible outcomes are "1s", therefore the probability of spinnin a 1 is:

The probability of spinning a 1 is 1 in 3 or 33%.
Step-by-step explanation:
In this problem, all we have to do is replace x and y with the values we've been given.
It can be helpful to think of 3x as 3 * x (which is the same exact thing), so I'll write it out that way.
3*x - 4*y
(replace)
3*4 - 4*3
(multiply (doing this step first because of PEMDAS))
12 - 12
(subtract)
0
Answer:
0
Answer:
200m
Step-by-step explanation:
To find volume you multiply each side, length, width, and height. 5 times 4 is 20, and 20 times 10 is 200