Answer:
a. $64 per hour
b. Tortilla chips = $9.60, Potato chips = $7.68 , Pretzels = $6.40
Explanation:
Plant-wide factory overhead rate = Budgeted Overhead / Budgeted Activity
Calculation of Budgeted Overheads :
Hint : Consider only Indirect Manufacturing Costs
Factory depreciation $13,645
Indirect labor $33,817
Factory electricity $3,856
Indirect materials $8,010
Total $59,328
Calculation of Budgeted Hours :
Tortilla chips (1,500 × 0.15) = 225
Potato chips (3,600 × 0.12) = 432
Pretzels (2,700 × 0.10
) = 270
Total = 927
Plant-wide factory overhead rate = $59,328 / 927
= $64 per hour
Factory overhead allocated to each of the three products :
Tortilla chips (0.15 × $64) = $9.60
Potato chips 0.12 × $64) = $7.68
Pretzels (0.10 × $64) = $6.40