Answer:
Option D
Explanation:
In simple words, moral hazard refers to the situation when an individual do not act with full responsibility due to the fact that any loss from their behavior will be borne by some third party.
Thus, by assessing the employees before employment by a test will help to decide the employer if the individual is worthy of the job or not. Thus, efficient employees will be selected and less mistakes will occur.
I believe the answer you're looking for is $145. explanation is marginal cost equals change in total variable cost/change in quantity. So it would be $9.4 million - $6.5 million = $2.9 million/20,000. So $2,900,000÷20,000= $145
Answer: The correct answer is "c. bounded rationality".
Explanation: Jacob's decision is an example of bounded rationality, because according to the theory of limited rationality, people make decisions only partially in a rational way because of our cognitive, information and time constraints.
The parol evidence rule will not permit evidence of an oral agreement that is inconsistent with a written term, for as to that term the contract is integrated.
"Parol evidence” is generally oral evidence. It is beneficial and may be admitted under certain circumstances after the parties agree to a final written agreement. For example, if the parties to the contract made a mistake, such as omitting or mistakenly listing a term, parol evidence may be considered.
The parol evidence rule is an evidentiary rule in contract disputes which generally makes evidence of agreements outside the parties' written contract inadmissible. That is, under the parol evidence rule any agreement that is not contained within the written contract is inadmissible in court.
Learn more about Oral evidence at
brainly.com/question/11190327
#SPJ4
<em>The complete question reads;</em>
When you want to save time recording progress and don't mind slightly less accuracy, which progress reporting approach would you choose?
a. tracking work and remaining work at the task level
b. tracking % complete at the task level
c. tracking work at the assignment level
d. tracking % complete at the assignment level
Answer:
<u>d. tracking % complete at the assignment level</u>
Explanation:
Remember, tracking the percent of completion of the assignment level would be indicating an overview of the entire assignment which may be slightly less accurate compared to the other listed options.
Thus, to save time recording progress this is the best viable option.