Answer:
c) finish-to-start; start-to-start
Explanation:
Project dependencies are the time relationships between a predecessor and a successor in project management. In other words, these dependencies describe which activity among the two needs to start earlier or later and when it needs to start or finish compared to the other one.
The most common type of dependency in all projects (no matter the nature or industry) is the finish-to-start one, where the activity A needs to be completed before activity B starts, e.g. base nail polish has to be put before the top coat gets put on the nails.
The second most common type of dependency is the<em> start-to-star</em>t one, where two activities need to start at the same time. This is common for activities where synchronization is paramount.
It can affect the company's ability to get a lending (borrow money). It can also affect the chances of finding an investor.
Answer:$10,350
Explanation:
3,450* 3 (month minimum) = 10,350
Answer:
55.58
Explanation:
Data provided in the question;
Initial demand per month, Q₁ = 3
Final demand per month, Q₂ = 5
Initial price, P₁ = $33,200
Final price, P₂ = $33,500
Now,
elasticity of demand using midpoint method is calculated as :
=
or
=
on substituting the respective values, we get
=
or
=
or
=
= 55.58