Answer:
630,000 units and 678,000 units
Explanation:
The computation of the equivalent units for material cost and for conversion cost is shown below:
For material cost
= Units transferred × completion percentage + ending work in process units × completion percentage
= 630,000 units × 100% + 120,000 units × 0%
= 630,000 units + 0 units
= 630,000 units
For conversion cost
= Units transferred × completion percentage + ending work in process units × completion percentage
= 630,000 units × 100% + 120,000 units × 40%
= 630,000 units + 48,000 units
= 678,000 units