1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
TiliK225 [7]
3 years ago
13

Armour, Inc., an advertising agency, applies overhead to jobs on the basis of direct professional labor hours. Overhead was esti

mated to be $216,000, direct professional labor hours were estimated to be 18,000, and direct professional labor cost was projected to be $270,000. During the year, Armour incurred actual overhead costs of $212,000, actual direct professional labor hours of 17,500, and actual direct labor cost of $317,000. By year-end, the firm's overhead was:
a. $2,000 underapplied.
b. $6,000 underapplied.
c. $4,000 underapplied
d. $2,000 overapplied
e. $4,000 overapplied.
Business
1 answer:
monitta3 years ago
3 0

Answer:

a. $2,000 underapplied.

Explanation:

Estimated Overhead = $216,000

Estimated Professional hours = 18,000

Predetermined overhead rate = $216,000 / 18,000 = $12 per hour

Actual Professional hours = 17,500

Overhead applied = $12 x 17,500 hours = $210,000

Actual overhead = $212,000

Under applied overhead = Applied overhead - Actual overhead

Under applied overhead = $210,000 - $212,000

Under applied overhead = $2,000

You might be interested in
An agent must disclose an agency relationship: a. Within 5 days of obtaining a listing. B. Within 5 days of procuring a buyer. C
snow_lady [41]
D. As soon As practical
8 0
2 years ago
Cosi Company uses a job order costing system and allocates its overhead on the basis of direct labor costs. Cosi expects to incu
fenix001 [56]

Answer:

156.6%

Explanation:

Given:

Cosi Company's Incurred over head for the next period = $830,000

Expected labor hours = 53,000

Cost of labor = $10.00 per hour

Thus,

Total labor cost = 53,000 × $10.00 = $530,000

Now,

the Cosi Company's predetermined overhead rate will be calculated as:

Predetermined overhead rate =  Incurred overhead / Total labor cost

on substituting the respective values, we get

Predetermined overhead rate = ( $830,000 / 530,000 ) = 1.566

or

Predetermined overhead rate = 1.566 × 100% = 156.6%

4 0
3 years ago
In a statement of cash flows, the sum of cash inflows and outflows is equal to:
PolarNik [594]

When in the statement of cashflows, the cash inflows and the outflows are added, the result is the <u>change </u><u>in the </u><u>cash balance. </u>

The statement of cashflows shows the movement of cash in a company and how much cash the company is left with at the end of the period.

The statement includes:

  • Cash outflows which are deductions
  • Cash inflows which bring in money

Cash outflows are denoted in negatives and when added to cash inflows, show the change in the cash that the company has / its balance.

In conclusion, adding the cash inflows and outflows shows the change in cash.

<em>Find out more at brainly.com/question/15214250. </em>

5 0
2 years ago
State Street Beverage Company issues​ $805,000 of​ 9%, 10-year bonds on March​ 31, 2017. The bonds pay interest on March 31 and
Citrus2011 [14]

Answer:

Option (B) If the market rate of interest is 10%, the bonds will issue at a discount

Explanation:

Interest rate risk is defined as the risk changing which, interest rates will affect bond prices. When current interest rates are greater than a bond's coupon rate, the bond will be sold below its face value at a discount. When interest rates are less than the coupon rate, the bond can be sold at a premium--higher than the face value.

7 0
3 years ago
Greengage, Inc., a successful nursery, is considering several expansion projects. All of the alternatives promise to produce an
Ilia_Sergeevich [38]

Answer:

A. Project A

B. Project A has lowest Standard Deviation

C. Project D

Explanation:

A.

The higher the range, the more risky the project is. Based on the table, project A has the smallest range, and therefore is the least risky based on range.

B.

The standard deviation is not scale-free, i.e. it is not adjusted for the level of returns. Hence, a project that has the same distribution of returns, but a higher average return, will have a higher standard deviation. But the project is not any more risky. Hence, the standard deviation might not be an appropriate measure of risk.

C.

The Coefficient of Variation (CV) is calculated as follows:

CV = Standard deviation / expected return

Applying this formula, the coefficient of variation for each project is:

Project A: 2.9% / 12.0% = 0.242

Project B: 3.2% / 12.5% = 0.256

Project C: 3.5% / 13.0% = 0.269

Project D: 3.0% / 12.8% = 0.23 4

Based on the coefficient of variation, project D has the lowest coefficient. It means that the project has the lowest risk per unit of return generated, and thus is the best project and should be chosen.

4 0
3 years ago
Other questions:
  • Rennin Dairy Corporation is considering a plant expansion decision that has an estimated useful life of 20 years. This project h
    8·1 answer
  • Jason's Outdoors manufactures two products: snow skis and water skis. Jason's managerial accountant suspects that product cost d
    14·1 answer
  • Central planning is a key characteristic of which economic​ system?
    13·2 answers
  • The Financial Services Modernization Act allowed bank holding companies to open insurance underwriting affiliates and allowed in
    7·1 answer
  • Properties of numbers 7(x-3)=7x-21
    15·1 answer
  • 18. A company is in its first month of operations. On January 15, the company receives $600 from customers who will receive 10 v
    13·1 answer
  • How important is following up with your potential employers after an interview?
    6·2 answers
  • What is my level of education if I just finished 10th grade?
    7·2 answers
  • At Eady Corporation, maintenance is a variable overhead cost that is based on machine-hours. The performance report for July sho
    5·1 answer
  • You are asked to study the causal effect of hours spent on employee trainingâ (measured in hours per worker perâ week) in a manu
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!