Answer:
materials quantity variance: 1,200 unfavorable
Explanation:
std quantity 5400.00
actual quantity 6000.00
std cost $2.00
difference -600.00
quantity variance $(1,200.00)
The difference between standard and actual quantity is negative. We used more pounds than expected, the variance will be unfavorable.
600 extra pounds at $2.00 each = 1,200
The control systems used in international firms are;
- personal
- bureaucratic
- output
- Scientific
<h3>What is the control system?</h3>
A control system serves as set of mechanical or personal devices that are used in regulating other other devices or systems.
In international firms this control system helps to monitor the ethics, standards that are required by the international firm in relation with other firms across the globe.
Learn more about control system at;
brainly.com/question/14364696
Often, controllers oversee the accounting, audit, and budget departments. Treasurers and finance officers direct their organization's budgets to meet its financial goals. They oversee the investment of funds. They carry out strategies to raise capital (such as issuing stocks or bonds) to support the firm's expansion.
i hope this helps you out!!!!
Answer:
Option (B) is correct.
Explanation:
Given that,
Required reserve ratio = 15 percent
Bonds sell to public = $25.5 million
Bank reserves decreases by $25.5 million because of the purchasing of bonds from the Fed.
Money multiplier:
= 1/Required reserve ratio
= 1/0.15
= 6.67
Therefore, the money supply decreases by:
= Money multiplier × $25.5 million
= 6.67 × $25.5 million
= $170 million
Answer:
The correct answer is letter "B": seeks to ensure the future performance of the project work is aligned with the project management plan.
Explanation:
Preventive actions are defined as those that aim to mitigate risks inherent in the operations of a business. Preventive actions lead to entities creating contingency plans that allow them to have certain strategies in front of unexpected situations that could harm the firm's operations.
<em>The project risk management plan is the reference that prevention actions take at the moment of recognizing the set of activities that should be followed to ensure the optimal future performance of a project.</em>