Answer:
the scope statement; deliverables
Explanation:
"Decomposing" a project will ensure an efficient way of accomplishing the project's goal. Before doing this, it is important to know what "the scope statement" is and the "deliverables" (multiple tasks in the production).
"The scope statement" allows one to know what should be included in the decomposition. It also tells <em>when you are going to stop breaking down </em>and what tasks are to be included. Once you know this, it<em> becomes easier to decompose a projec</em>t with<u> one deliverable at a time.</u> The scope will also be further clarified.
So, this explains the answer.
Answer:
(2). Although her request to telecommute was denied, Lindsay will begin a flextime schedule in two weeks.
Explanation:
The second choice would be the most preferred as it conveys the idea in a formal and precise manner. <u>The complex sentence beginning with the subordinate clause already hints the listener that the key message is yet to come. It helps him/her in understanding the intended message without any confusion</u>. The first sentence fails to create that specificity as it connects two independent ideas which remove the listener's focus from the main idea i.e. 'she will begin a flextime schedule in two weeks.' Thus, option (2) adopts the correct format and sentence structure to deliver the message effectively, efficiently, and precisely.
It must gain 1.375 pounds more before it can leave.
I<span>f the container store owners/managers were to walk around and personally thank each employee for doing a good job, then this would be a motivating factor. This action exhibits a good environment as well for employees to foster as they're performances are acknowledged by their employers. if this goes on, this will inspire many employees to alleviate their status.</span>