Answer:
The overview of the problem is listed throughout the section below on explanation.
Explanation:
The Journal entry is given below:
<u>No Transaction General journal Debit($) Credit($)</u>
1 1 Overhead of factory 120000
Some other accounts 120000
2 2 Process inventory's work 185500
Overhead of a factory 185500
Answer:
Total sales tax payable:170, sales :2000
Explanation:
Sale price x sales tax rate = sales tax payable
2000 x .085 (6%+2.5%) = 170
it doesn’t say so I’m assuming that the 2,000 credit sale does NOT include the sales tax due.
Answer: C) $2,000 per week.
Explanation:
The slope of the project refers to the additional amount that it would cost to be able to finish the project faster than schedule.
In the question, the construction activity is for 14 weeks at a rate of $5,000 for the laborers per week. If you wanted to reduce this project duration to 10 weeks, you will have to spend an additional $2,000 more per week.
This $2,000 is therefore the slope of the activity.
Answer:
The correct answer is A: All of the answer are correct
Explanation:
ABC defines production as consisting of a variety of activities, and it assigns costs to those activities. An activity cost pool is an aggregate of all the costs associated with performing a particular business task, such as making a particular product. By pooling all costs incurred in a particular task, it is simpler to get an accurate estimate of the cost of that task.
Cost pool is created for those costs more closely aligned with the production of goods or services. It is very common to have separate cost pools for each product line. If production batches are of greatly varying lengths, then it has to consider creating cost pools at the batch level, so that it can adequately assign costs based on batch size.
To conclude, the creation of a cost pool and the subsequent assignment of costs will vary according to the length of production and the possibility to discriminate and assign costs.