Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
When x = - 4 then
y = 1/2(-4) -6
y = -2 - 6
y = -8
solution (-4, -8)
answer is
B. (-4, -8) second choice
Answer:
<h3>x = -3</h3>
Step-by-step explanation:
First let us get the equation of the coordinates
y-y0 = m(x-x0)
Using the coordinates ( - 3, 2 ), ( - 1, 0 )
m = 0-2/-1-(-3)
m = -2/2
m = -1
Substitute m = -1 and (-1, 0) into the formula
y - 0 = -1(x+1)
y = -x-1
f(x) = -x-1
Since f(x) = 2
2 = -x-1
-x = 2+1
-x = 3
x = -3
Hence the value of x is -3

Step-by-step explanation:
We know that
cos 2x = 2cos²x - 1
So we have

Substituting 

Answer:
x=12
Step-by-step explanation:
3.6x=1.6x+24
We simplify the equation to the form, which is simple to understand
3.6x=1.6x+24
We move all terms containing x to the left and all other terms to the right.
+3.6x-1.6x=+24
We simplify left and right side of the equation.
+2x=+24
We divide both sides of the equation by 2 to get x.
x=12