Answer: Total Variable Costs = $110130
Explanation:
The question in incomplete. Requirements were not provided in the question, as a result it is not clear what the question requires us to do. We will assume the question requires us to calculate Total variable costs since There is nothing in the question that talks about fixed costs.
Total Variable Costs
Manufacturing costs
Direct Material Per pound = $2.95
Direct Material used = 27800 pounds
Direct Material Cost = 27800 x 2.95 = $82010
Direct Labor
Direct Labor cost per hour = $6.20
Direct Labor hours = 3800
Direct Labour Cost = 3800 x $6.20 = $23560
Variable Manufacturing overhead cost = $4560
Total Variable Costs = Direct Material cost + Direct labor costs + Variable Manufacturing overhead
Total Variable Costs = $82010 + $23560 + $4560
Total Variable Costs = $110130
Answer:
Explanation:
If a company(Marriott in this case) uses a single hurdle rate to decide whether an investment should be undertaken or not, some projects that need to be accepted would end up being rejected and vice versa. For example,
if Marriott's hurdle rate is 10% and it's evaluating
project A with a 15% cost of capital &
project B with a 6% cost of capital .
Evaluation:
Project A would probably lead to a negative NPV because the cost of capital is higher (meaning it is riskier than the firm) hence could be rejected, but using the company hurdle rate of 10% to evaluate it could make its NPV positive. This would ignore the actual additional risk of the project.
Usually they start out small as family-owned restaurants and gradually increase until chains are created
Answer:
D. Consumption by $80 billion.
Explanation:
Marginal propensity to Save = 1 / MPS
= 1 / 0.2
= 5
= $20 billion × 5
= $100 billion
= $100 - $20
= $80 billion
Therefore, a $20 billion rise in investment spending will increase consumption by $80 billion.
Answer:
$34,000 Units
Step by Step Explanation:
Direct Material Quantity Variance
= SP x (AQ – SQ Allowed)
Therefore:
SQ allowed: $56,000 units x 4 lbs = $224,000 lbs.
Direct Material Quantity Variance: $8.50 x ($228,000 lbs – $224,000 lbs) = $34,000 Units
The direct material quality variance is $34,000 Units