Answer:
Explanation:
The computation of expense amount is shown below:
= Expenses - adjusted prepaid expense + adjusted accrued expense
= $35,200 - $500 - $450
= $34,250
The adjusted prepaid expense is computed by
= Ending balance of prepaid expense - beginning balance of prepaid expense
= $1,800 - $1,300
= $500
And, the The adjusted accrued expense is computed by
= Ending balance of accrued expense - beginning balance of accrued expense
= $1,200 - $1,650
= -$450
<u>Explanation:</u>
First, remember that the difference between <em>normative and positive economic analysis</em> is that;
Normative analysis take a somewhat neutral view by stating how the world should be. While
The Positive analysis states the facts. That is, it describes the world as it is.
<u>
Thus, a </u><u>Normative analysis</u><u> of the consequence of minimum wage would be the following statements:</u>
c. In some cities such as San Francisco and New York, it would be impossible for low−skilled workers to live comfortably in the city without minimum wage laws.
d. The gains to winners of a minimum wage law should be valued more highly than the losses to losers because the latter primarily comprises businesses.
<u>And a </u><u>Positive analysis</u><u> of the consequence of minimum wage would be the following statements:</u>
a. The minimum wage law causes unemployment.
b. A minimum wage law benefits some groups and hurts others.
Answer:
Particulars Amount
Provision for uncollectible $6,080 ($76000*8%)
Less: Provision already made <u>$1,000</u>
Provision to be made <u>$5,080</u>
Date Particulars Debit Credit
31-Dec Bad Debts $5,080
To Allowance for Doubtful Accounts $5,080
(Being the adjusting entry to estimate bad debts)
<span>The fact that Kellog is increases its promotion expenditure to counteract competitive responses means that </span>Kellogg's is in the maturity stage of the product life cycle. The maturity stage us the third stage of the product life cycle, and comes a<span>fter the </span>Introduction<span> and </span>Growth<span> stages.
</span>In this stage the companies are focused on maintaining their market share in the face of a number of different challenges.
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.