Answer: 45 containers
Explanation:
The number of containers needed is calculated by:
= (Expected demand during Lead time + Safety Stock) / Container Capacity
Expected demand during Lead time = Daily demand * Lead time
= 2,500 * 3
= 7,500 units
Safety stock = 1.5 days * 2,500
= 3,750 units
Number of containers needed:
= (7,500 + 3,750) / 250
= 45 containers
Answer: (B) Location economies
Explanation:
According to the question, the gear-one autos inc. basically acquire the benefits of the location economies. The location economies is effective strategy in the economics used in an organization for determining the location.
The main aim of the location economics is that it producing the identical products by using the consistent strategy. The location economics helps the organization in the latest development.
Therefore, Option (B) is correct.
Answer:
$11,026 Favorable
Explanation:
The computation of the spending variance for plane operating costs in November is shown below:
= Budgeted cost - Actual cost
= [(84 × $3,160) + (252 × $18) + $593,00] - $318,250
= $329,276 - $318,250
= $11,026 Favorable
Answer:
A) $560 million
Explanation:
First lets calculate the NPV of the cash stream by this investment,
PV Cash stream = Cash flow/ (r-g), where r = avg cost of capital and g = growth of the cash stream.
PV = 50 / (0.09 - 0.04) = $1000 million
We assume that external finance issuance costs are payable as a part of initial outlay of the project and so,
Total initial outlay = 420 + 20 = $440 million
NPV of the project then,
NPV = 1000 - 440 = $560 million
Hope that helps.
No
Oh
And
I’m just doing this so I can