Answer:
Gain/loss= $1,000 loss
Explanation:
Giving the following information:
Original price= $54,000
Accumulated depreciation= $28,000
Seling price= $25,000
The gain or loss from selling an asset depends on the book value.
Book value= original price - accumulated depreciation
Book value= 54,000 - 28,000= 26,000
If the selling price is higher than the book value, the company gain from the sale.
Gain/loss= 25,000 - 26,000= $1,000 loss
Answer:
The correct answer is letter "B": unfavorably; increases.
Explanation:
As a measure to control inflation in the economy, the Federal Reserve (Fed) tends to <em>increase </em>the interest rate. This to have banks request fewer loans from the central bank which will result in offering fewer credits to individuals. If people have fewer sources of debt, the possibilities that an economic bubble -<em>continuous increase in price due to continuous increase in demand</em>- appear decreases.
However, if people have fewer sources of debt, private investment decreases, causing an <em>unfavorable </em>panorama for financial institutions offering large portfolios of assets.
Answer:
Year Cash Flow (A) Cash Flow (B)
0 -37,500 -37,500
1 17,300 5,700
2 16,200 12,900
3 13,800 16,300
4 7,600 27,500
1) Using an excel spreadsheet and the IRR function:
IRR project A = 20%
IRR project B = 19%
2) Using the IRR decision rule, Bruin should choose project A.
3) In this case, since the length of the projects is only 4 years, then there should be no problem with the IRR decision rule, but for projects with longer time lengths, the discounts rates might vary and the best option is to use the modified internal rate of return (MIRR). But in this case the NPV of project B is higher, then Bruin should probably project B because it has a higher NPV. The NPV is always more important then the IRR.
4) Again using an excel spreadsheet and the NPV function:
NPV project A = $6,331
NPV project B = $8,139
5) first we must subtract cash flows from A by the cash flows from B:
1 $11,600
2 $3,300
3 -$2,500
4 -$19,900
then we calculate the IRR = 16%
Bruin should be indifferent between the two projects at a 16% discount rate. That means that at discount rates above 16%, you should choose project A, but at discount rates below 16%, you should choose project B
Answer:
Please consider the following explanation
Explanation:
a. EOQ = 560 units
b. 58800 units/560 units = 105 orders
c. EOQ/2 = 560/2 = 280 units (average inventory)
d. 105 orders × $4 ordering cost = $ 420
280 units × $1.50 carrying cost per unit = 420
Total costs = $840
Answer:
The correct answer is A: All of the answer are correct
Explanation:
ABC defines production as consisting of a variety of activities, and it assigns costs to those activities. An activity cost pool is an aggregate of all the costs associated with performing a particular business task, such as making a particular product. By pooling all costs incurred in a particular task, it is simpler to get an accurate estimate of the cost of that task.
Cost pool is created for those costs more closely aligned with the production of goods or services. It is very common to have separate cost pools for each product line. If production batches are of greatly varying lengths, then it has to consider creating cost pools at the batch level, so that it can adequately assign costs based on batch size.
To conclude, the creation of a cost pool and the subsequent assignment of costs will vary according to the length of production and the possibility to discriminate and assign costs.