Answer:
is not attainable for this nation
Explanation:
The Production possibilities frontiers is a curve that shows the various combination of two goods a company can produce when all its resources are fully utilised.
The PPC is concave to the origin. This means that as more quantities of a product is produced, the fewer resources it has available to produce another good. As a result, less of the other product would be produced. So, the opportunity cost of producing a good increase as more and more of that good is produced.
Point outside the curve or to the right of the curve means that the production level is not attainable given the level of resources
Points inside the production possibilities curve means that the nations resources are not being fully utilised
Factors that cause the PPF to shift
1. changes in technology.
2. changes in available resources.
3. changes in the labour force.
Answer:
C) scenario analysis considers the effect on NPV of changing multiple project parameters.
Explanation:
Scenario analysis is used to determine the effect on the end result if several parameters are changed . Sensitivity analysis on the other hand involves the effect on the end result due to change in one parameter. With regard to net present value, the scenario analysis on the project will based on effects of changing multiple parameters for example how NPV will change due to increase in price of the products sold, changes in inflation rate and changes in corporate taxes.
Answer:
a. continue with the project provided that the additional solar electricity is worth more than $10 million.
Explanation:
It is provided that after cost overruns of the project is $10 million, which can never be recovered, thus, it is a kind of sunk cost.
Sunk cost is the cost which is made previously, and now in no manner will affect the decision, as cannot be recovered.
Therefore, such cost is ignored.
Further provided additional cost will be $12 million, therefore, now the society shall make a rational choice whether to continue the project providing solar electricity of $10 million, as in case of amount of solar energy is $32 million or $22 million, then the choice is obvious to accept,
Rational choice will be for solar electricity worth $10 million.
Therefore, correct statement is
a. continue with the project provided that the additional solar electricity is worth more than $10 million.
Answer:
$180,000
Explanation:
Given that
Current E & P = $240,000
Distribution to Larry = $450,000
The computation of current E & P is allocated to Larry's distribution is shown below:-
Current E & P is allocated to Larry's distribution = (Current E & P × Distribution to Larry) ÷ Total distribution
= ($240,000 × $450,000) ÷ $600,000
= $108,000,000 ÷ $600,000
= $180,000
The answer to the given question above would be the fourth or last option. A dividend is defined as the money that a company regularly <span>(typically quarterly) pays shareholders from its profits. Hope this is the answer that you are looking for. Have a great day ahead!</span>