Answer:
135 days
Step-by-step explanation:
Often, we measure work in man·days. This piece of work requires ...
(45 man)·(90 days) = 4050 man·days
When there are only 30 men, the number of days required can be found by dividing this work by the number of men:
4050 man·days/(30 man) = 135 days
_____
Another approach is to realize the time is inversely proportional to the number of men. If the number of men is 30/45 = 2/3 the original, then the time will be 3/2 the original, or ...
(3/2)·90 days = 135 days.
Order of Operations, I'm pretty sure
The algebraic expression for the mathematical statement given as 4 more than the difference of 12 and a number j is 4 + 12 - j
<h3>How to determine the arithmetic expression?</h3>
The mathematical statement is given as:
4 more than the difference of 12 and a number j
4 more than means 4 +.
So, we have:
4 + the difference of 12 and a number j
the difference of 12 and a number j means 12 - j
So, we have
4 + 12 - j
Hence, the algebraic expression for the mathematical statement given as 4 more than the difference of 12 and a number j is 4 + 12 - j
Read more about algebraic expression at
brainly.com/question/4344214
#SPJ1
Answer:
x=12
Step-by-step explanation:
Since the triangle is isosceles, the 2 base angles are congruent.
Also, the interior angles of a triangle add up to 180.
32+7x-10+7x-10=180.
Solve.
14x+32-20=180
14x+12=180
14x=168
<u>x=12</u>