It would be false, because they don’t go into the same category
Answer:
Cost Variance (CV) for the project is negative $77.5
Explanation:
The total amount budget for all 3 activities = Activity A worth $200 + Activity B worth $75 + Activity C worth $200 = $475
The total value completed = activities cost x % complete = $200*100% + $75*90% + $200*75% = $417.5
The actual cost till now = $200 + $120 + $175 = $495
The cost variance = The total value completed - The actual cost till now = $417.5 - $495 = ($77.5)
Answer and Explanation:
The computation is shown below:
a. The amount in 2 years later is
As we know that
Amount = Principal × (1 + rate)^time period
= $10,675.50 × (1 + 6.5% ÷ 2)^2× 2
= $10,675.50 × (1 + 0.03125)^4
= $10,675.50 × 1.130982
= $12,073.80
b. Now the compound interest is
= Final Amount - principal amount
= $12,073.80 - $10,675.50
= $1,398.30
The above formulas should be applied