1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
melisa1 [442]
3 years ago
8

Jose has 9 more comic books than Robin. Robin has 5 more comic books

Mathematics
2 answers:
vova2212 [387]3 years ago
6 0
A. 
jose has 23 then minus nine for robin and she has 14 and minus 5 for lee and boom nine.
rjkz [21]3 years ago
3 0
The answer to your question is A
You might be interested in
I will give brainleist
Pachacha [2.7K]

Answer:

In which one? What is nth?

Step-by-step explanation:

6 0
4 years ago
A business has a 200 ft wall and places 6 letters on the center of an exterior wall to spell sale. if there is 1 ft betweeen eac
sergejj [24]
How wide are the letters
8 0
3 years ago
A partner calls for 2 1/4 yard of material and 1 1/4 yards of lining.how much toyal fabric needed?
geniusboy [140]
3 1/2 

2 1/4+ 1 1/4 = 3 2/4 
or 3 1/2
7 0
4 years ago
Help<br><br>solve question A and B<br><br>I really appreciate it... I will mark as brainliest​
lina2011 [118]

A 2:4

B  4:6:12

C 0.6:2.4

Distance from school to shop is 12 km

6 0
3 years ago
Read 2 more answers
You have just used the network planning model and found the critical path length is 30 days and the variance of the critical pat
joja [24]

Answer:

0.726 is the probability that the project will be completed in 33 days or less.

Step-by-step explanation:

We are given the following information in the question:

Mean, μ = 30 days

Variance = 25 days

Standard Deviation,

\sigma = \sqrt{\text{Variance}} = \sqrt{25} = 5

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.

Formula:

z_{score} = \displaystyle\frac{x-\mu}{\sigma}

P(completed in 33 days or less)

P( x \leq 33) = P( z \leq \displaystyle\frac{33 - 30}{5}) = P(z \leq 0.6)

Calculation the value from standard normal z table, we have,  

P(x \leq 33) = 0.726 = 72.6\%

0.726 is the probability that the project will be completed in 33 days or less.

8 0
3 years ago
Other questions:
  • Please help I will give brainliest to the first person who answers both correctly
    7·1 answer
  • Is 5.56 greater than 5 1÷7​
    6·1 answer
  • the faucet leaks water at a rate of 5^-5 litre per second. how many litres of water will leak from the faucet in 1 hour
    14·1 answer
  • What is the average rate of change for the line graphed in the figure above
    15·1 answer
  • Afton made a chicken dish for dinner. She added a 10 ounce package of vegetables and a 14 ounce package of rice to 40 ounces of
    10·1 answer
  • HELPPPP PLEASE!!!!!!!!!!!!!!!!!!!
    10·2 answers
  • Pleaseeeehelppppppppp
    11·1 answer
  • Is this correct?? So, basically, it asking for a decimal equivalent to 920.35
    8·1 answer
  • I need help plz plz help me
    6·2 answers
  • 295 words in 6 minutes ; What are the words/min.? (round to the nearest tenth)
    11·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!