Find x to the nearest hundredth.

Mathematics
1 answer:
uysha [10]3 years ago
7 0

Answer:23.78cm

Step-by-step explanation:

You might be interested in
(Correct answer only please)
andriy [413]

Answer: Choice A)  Add 3.8 to both sides of the equation

Explanation:

If we knew the value of w, then we would replace it and apply PEMDAS.

However, we don't know the value of w, so we undo each step of PEMDAS going backwards.

We start with the "S" of PEMDAS, and undo the subtraction. To undo subtraction, you apply addition. To undo that "minus 3.8" we add 3.8 to both sides.

4 0
3 years ago
Read 2 more answers
Which shows the domain range of these function?
Bas_tet [7]

Answer: domain: (-oo,oo) range: (0,oo)

Step-by-step explanation:

7 0
3 years ago
Read 2 more answers
Suppose you have $245. If you decide to spend it all on ice cream, you can buy 70 pints. If the price of a glass of lemonade is
guajiro [1.7K]

Answer:

198

Step-by-step explanation:

7 0
3 years ago
It takes 9 builders 54 days to complete a house.
Dima020 [189]

It would take 6 builders  36 days to complete the same house.

<h3>Who are builders?</h3>

Builders are those person whose job is to build or repair houses and other buildings.

We have,

9 builders take 54 days to complete a house.

So,

1  builder will take  (\frac{54}{9})  days to complete a house,

In the same way,

6  builder will take  (\frac{54}{9}*6)  days to complete a house,

i.e.

6  builder   =(\frac{54}{9}*6)= 36 days.

Hence, we can say that it would take 6 builders  36 days to complete the same house.

To know more about  builders and work click here

brainly.com/question/16924313

#SPJ2

5 0
1 year ago
Read 2 more answers
Someone please help!!! Can’t find this one anywhere!!! please and thank you!!!!!!!
Tema [17]

\dfrac{ 2+ 2i}{5+4i}\\\\\\=\dfrac{(2+2i)(5-4i)}{(5+4i)(5-4i)}\\\\\\=\dfrac{10-8i + 10i -8i^2}{5^2 -(4i)^2}\\\\\\=\dfrac{10+2i +8}{25+16}~~~~;[i^2 =-1]\\\\\\=\dfrac{18+2i}{41}\\\\\\=\dfrac{18}{41} + \dfrac{2}{41}i

4 0
2 years ago
Other questions:
  • Please help last question !!!!!!<br> Please help me !!!!!!!
    15·1 answer
  • Name two congruent angles that measure 15
    5·1 answer
  • Water is withdrawn from a conical reservoir, 8 feet in diameter and 10 feet deep (vertex down) at the constant rate of 5 ft³/min
    11·1 answer
  • Write an appropriate inverse variation equation if y = 5 when x = 3
    11·1 answer
  • Solve y = ax2 + c for x
    12·2 answers
  • A 12 inch candle and an 18 inch Candle are lit at 6 p.m. The 12 inch candle burns 0.5 inches every hour. The 18 inch candle burn
    8·1 answer
  • Jake and Abigail worked a job together. Jake earned 3/4 of what Abigail did. Together they earned $140. How much did each earn?
    13·2 answers
  • For what values of x∈[0,2π] does the graph of y=x+2cosx have a horizontal tangent?
    9·1 answer
  • Fill in the blanks to complete the special rule for inequalities.
    8·1 answer
  • Can someone help me with these problems, DUE today!
    9·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!