Answer:
Answer letter B
Masin sets his own work schedule
Answer:
False
Explanation:
The expected value of each course of action in a decision tree is not determined by starting at the beginning of the tree, instead it is a process because you need to make a desition and in some extend you espect to have some results but some of them are uncertain or unespected. in this kind of scheme Squares represent decisions, and circles represent uncertain outcomes. Then you need to calcule the desition nodes giving each option a cost or value, This will give you a value that represents the benefit of each decision. at the end calculating choose the option that has the largest benefit, and take that as the decision made. This is the value of that decision node.
Answer:
a. $164,000
Explanation:
The computation of the Altoon Manufacturing's sales for the year until the flood is given below:
= Cash collections + ending receivables - opening receivables
= $158,000 + $25,000 - $19,000
= $164,000
hence, the Altoon Manufacturing's sales for the year until the flood is $164,000
Therefore the first option is correct
Answer:
a. 105
b. For machining $130
For assembly $50
Explanation:
a. The computation of the company's current plant-wide overhead rate is shown below:-
Current plant-wide overhead rate = Total manufacturing overhead ÷ Total direct labor hours
= $1,050,000 ÷ 10,000
= 105
b. The computation of refined departmental overhead rates is shown below:-
Departmental overhead cost = Overhead cost of department ÷ Cost driver of department
For machining
= $650,000 ÷ 5,000
= $130
For Assembly
= $400,000 ÷ 8,000
= $50
Answer:
Please find the detailed answer as follows:
Explanation:
Consider the table attached in the excel.
The above are the requirements of the units of material if demand of 8080 units of S has to be completed.
The requirement of units of U for maintenance is given in the second table.
As the lead time for S is two weeks the components should be ready by the fifth week.
As the lead time for components T and U both is 2 weeks their components should be ready by the third week.
Hence in the first week the required number of units of V, W, Y and Z are to be ordered as all of them are required in the third week.
The required number of units of X are to be ordered in the second week to be ready in third week.
The required units of U, Y and Z are to be ordered considering the requirement to make S plus the maintenance requirements.