Answer and Explanation:
The computation is shown below:
1. VaR = Expected return - z × Standard deviation
= 13% - 1.645 × 20%
= -19.90%
Therefore the option a is the correct answer.
2) Now the correlation coefficient is
Variance of the portfolio = (weight of A × Standard deviation 1)^2 + (weight of B × Standard deviation 2)^2 + (2 × weight of A × weight of B × Standard deviation 1 × Standard deviation 2 × correlation 1 and 2)
3.80% = (60% × 24%)^2 + (40% × 18%)^2 + (2 × 60% × 40% × 24% × 18% × correlation 1 and 2)
So the correlation is 0.583
Answer:
The making and delivery of the product.
Explanation:
Because in a factory it manufactures the product that they are making and send them to stores to sell the products for money.
Answer:
The entry is not required because the outcome is reasonably possible, not certain or probable. So IAS 37 says that the liability must not be recognized as the outcome is not reasonably certain or probable.
Explanation:
The liability must be included in the financial statement only if the outcome is certain or probable. In this scenario, the outcome is reasonably possible but neither certain nor probable in this situation. So the entry in the financial statement is not required. If the liability is of a huge amount then IAS 37 says that their must be a disclosure in the financial statement notes about the lawsuit.
Answer:
Units transferred out = 760
Explanation:
If we assume that all units are completed in the order of arrival i.e (FIFO), then the units transferred out is the sum of the opening inventory and the units started and completed in the period. The units started and completed in the period is referred to fully-worked.
Fully worked is computed as the units started in the period less the closing inventory .
Fully- worked = 800 - 240 = 560
The units transferred out = opening inventory + Fully-worked
= 200 + 560 = 760
Units transferred out = 760
Note we assumed that the units of the inventory( started last period i.e January) would be worked on first in the month of February before any other units. So, it is assumed completed by the end of February
Answer:
d. $1,875 unfavorable
Explanation:
Direct material quantity variance is computed as;
= (AQ - SQ) × SP
AQ = Actual quantity = 6,300 units
SQ = Standard quantity = 14,200 / 2 = 7,300 units
SP = Standard price = $0.80
Direct material quantity variance
= (6,300 - 7,300) × 0.80
= -1,000 × $0.80
= -1,875 unfavorable