Answer:
From the calculation below Up-Towne Movers just paid a dividend of $3.13
Explanation:
The price of share=D1/r-g
The Do is the dividend just paid which is the unknown in the equation
g is the dividend growth rate of 4.3%
r is the required return of 11.1%
The share price is $46.00
$46=Do/(11.1%-4.3%)
46=Do/0.068
by cross-multiplication the equation becomes
$46*0.068
=Do
Do=$46*0.068
Do=$3.13
The dividend just paid by Up-Towne Movers is $3.13 as calculated above from the share price equation
Answer:
"D" is the correct answer.
All of these.
Explanation:
NOTE: in this question, options part is missing, The option for the following question is :
b. Additions to business stock
c. firms' buy of equipment
d. All of the above
Gross Domestic Product is the overall financial or retail value of all completed production of goods and services in a specific period within a country.
formula to calculate GDP is as follow
GDP = C + I + G + NX
where C stands for Private consumption.
I stands for investment
G stands for government consummation
NX for net export (total export - total import)
GDP use to calculate countries total gross production during a particular year.
Answer:
MRPL= $200 = wage rate when there are 5 workers
and MRPL = $1,200 = wage rate when there are 2 workers.
Explanation:
The computation of unionized is shown below:-
Marginal revenue product of labor = Marginal product × Price per unit
Workers Total Production Marginal Product MRPL
(per day)
a b b × $8
0 0
1 200 200 $1,600
2 350 150 $1,200
(350 - 200)
3 450 100 $800
(450 - 350)
4 500 50 $40
(500 - 450)
5 525 25 $200
(525 - 500)
6 510 -15 -$120
(510 - 525)
From the above table MRPL = $200 = wage rate when there are 5 workers
and MRPL = $1,200 = wage rate when there are 2 workers.
Answer:
Listing the consequences of each option.
Explanation:
Answer:
Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.
Explanation:
activity A =
normal time (NT) = 5 days
Normal cost (NC) = $0
crash time (CT) = 3 days
Crash cost (CC) = $500
crash cost per day = [CC - NC]/[CT - NT] = $250/day
activity B:
normal time (NT) = 6 days
Normal cost (NC) = $0
crash time (CT) = 4 days
Crash cost (CC) = $50
crash cost per day = [CC - NC]/[CT - NT] = $25/day
activity C:
normal time (NT) = 8 days
Normal cost (NC) = $0
crash time (CT) = 3 days
Crash cost (CC) = $1000
crash cost per day = [CC - NC]/[ CT- NT] = $200/day
The activity that takes the least cost to speed up is the first one to be crashed. from the computations, activity B takes the least cost to speed up, so the project manager should crash activity B first by 2 days.
Therefore, Acitivy B should be crashed first by 2 days and Activity B has a crash cost per days of $25, it will be crashed for a total of $50.