Answer:
c
Explanation:
nate should have chosen to ask the supplier for verification for the requisition order
Answer:
The after-tax cost is $23,940
Explanation:
For computing the after-tax cost, first we have to compute the present value which is shown below:
Present value = Bill payment × marginal tax rate
= $38,000 × 37%
= $14,060
So, after tax value would equal to
= Bill payment or Pre tax value - Present value
= $38,000 - $14,060
= $23,940
Answer: 9.7%
Explanation:
Given Data
Rf = Risk free return = 6%,
Rpm = Risk premium = 4%,
Beta = 0.9
Wd = Debt = 20%
rd = cost of debt = 8%
We = equity = 80%
Re = Rf + Beta (Rpm)
= 0.06 +0.9 (0.04)
= 0.096 * 100
= 9.6%
Unlevered Equity Cost ;
ReU= Wd × rd + We × re
= 0.20 × 8% + 0.80 × 9.6%
= 9.28%
Levered Equity Cost:
New Debt = 60%,
New Equity = 40%,
New rd = 9%
ReL = ReU + (ReU - rd) (D ÷ E)
= 9.28% + (9.28% - 9%) (0.60 ÷ 0.40)
= 0.097 * 100
= 9.7%
Answer:
The correct answer is (E) continued to pour money into the stock market in the belief that the American economy was
Explanation:
Inflation can affect cash flows to a greater or lesser extent, depending on their nature. Thus inflation could affect sales prices more, or costs. The entrepreneur generally fights inflation trying to reduce costs and maintain competitive prices, but he can not against generalized inflation in the economy, and consequently his cash flows could be, in real terms, increasingly lower, by the loss of the power to buy money. In this way, inflation encourages investments with rapid recovery and that require less capital investment.
Answer:
a. $6
b. $3204000
Explanation:
Given:
- Product X is 534,000 units
- cost for materials $1,441,800
- cost for labour: $1,762,200
(a) a standard cost
As we know standard cost is the cost of producing 1 unit and is recorded in a standard cost card. However, the cost of labor, materials and overhead are used to make a single unit, so
standard cost = unit variable cost = the total cost / the total number of unit.
In this situation, the overheading cost is not gven, so the total cost:
= The cost of labor + materials
= $1,441,800 + $1,762,200
= $3204000
=> standard cost = $3204000 / 534,000 = $6
(b) a budgeted cost represents the total costs
The total number of units * standard cost
= 534,000 * 6
= $3204000