Answer:
$ 49,640
Explanation:
The question is asking for PLANNING BUDGET
Planning Budget does not in anyway mean flexible budget.
So the quantity of units for Planning Budget would be what the company budgeted that is 7,300 units
The next step in the solution to the question will be to know the cost per unit. For Direct Labor the price given is $ 6.80 per unit
Total Direct Labor for May in the planning budget would be 7,300 X 6.80 = $ 49,640
Answer:
Cost of goods manufactured= $228,700
Explanation:
<u>To calculate the cost of goods manufactured, we need to use the following formula:</u>
cost of goods manufactured= beginning WIP + direct materials + direct labor + allocated manufacturing overhead - Ending WIP
cost of goods manufactured= 25,500 + (46,000 + 75,500 - 39,500) + 100,500 + (68,500 - 11,800) - 36,000
cost of goods manufactured= $228,700
We deduct the indirect material from overhead because it is already incorporated into direct materials.
Answer:
Two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
Explanation:
An Israeli physicist named, Eliyahu M. Goldratt developed the Critical Chain Project Management (CCPM) and introduced it in his book "Critical Chain" in 1997.
The CCPM is a project management methodology used by managers to better manage a project. The CCPM ensures that the project plan is feasible and immune from any uncertainty or statistical fluctuations.
In the CCPM activity network, there are no milestones and all non-critical activities are performed as late as possible.
CCPM adopts the use of drum buffers, so as to ensure extra safety is applied to a project immediately before using constrained resource.
According to Goldratt, two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
The answer is b-savings back
Answer:
a ) Probability of default of debt over the time to maturity is 12.92%
(b ) Expected loss: $39.53
(C ) Present value of expected loss is $45.59
Explanation:
a ) Probability of default of debt over the time to maturity is 12.92%
(b ) Expected loss: $39.53
(C ) Present value of expected loss is $45.59.
Values calculated as shown in my detailed step by step answer at the attachment.
please kindly refer to attachment.